Preparatory work for PV construction under way, first wind turbine erected
/ 03.11.2026
Construction work is progressing at Hybrid Park Löberitz. Preparatory work for the photovoltaic plant has been under way since 21 October 2026, including site set-up, access road construction and fencing. At the same time, the three new wind turbines are being erected. The first turbine is already in place, while the second is currently being assembled. The dismantling of the old turbines is also continuing.
First solar modules have arrived
Following the start of construction work on the wind farm, preparations are now under way on the site of the photovoltaic plant. Initial site set-up activities began on 21 October 2026, including the construction of access roads and the installation of fencing. Construction of the PV plant itself will begin once the support posts for the module mounting structures are driven into the ground. The first deliveries of materials are already under way. As a result, there may be some additional delivery traffic around the construction site during this period.
Protecting the ground during construction
Steel plates have been laid along the access routes to minimise the impact of heavy delivery vehicles on the ground. Before work began, the contractors involved also received instructions on soil protection requirements. Protecting existing utility lines is another important part of the construction preparations. The project team has coordinated with the operators of utility lines running through or immediately adjacent to the planned photovoltaic site that could be affected by the construction work. Initial joint site inspections and briefings have already taken place, with further appointments scheduled over the coming days. This coordination helps protect existing utility lines from damage and identify and prevent potential risks to people working on the construction site at an early stage.
What happens next on the PV construction site?
Preparatory work will continue over the coming weeks. This includes constructing the internal access roads, further site set-up activities and installing the fencing. Once these preparations are sufficiently advanced, construction of the photovoltaic plant itself will begin. The support posts for the mounting structures will first be anchored in the ground, providing the framework onto which the solar modules will later be installed. The next steps will involve installing the solar modules, laying cables and connecting the modules to the inverters. These convert the direct current generated by the modules into alternating current. Transformer stations will also be installed as construction progresses.
Progress continues on the wind farm
The three new wind turbines are being erected alongside the preparatory work for the PV plant. The first turbine is already standing, while the second is currently under construction. Assembly of the third turbine will follow. Once the turbines have been erected, work will begin on their internal systems. This includes installing the technical and electrical components and preparing the turbines for commissioning. According to the current schedule, the first wind turbines could begin operating towards the end of 2026. The dismantling of the five old wind turbines is also progressing. All five turbines have now been dismantled, and work is currently under way to break up their foundations.
Keeping safety in focus on site
A joint safety tour recently took place at the construction site, attended by representatives from management, occupational health and safety, and the project team. Participants discussed the ongoing work and potential safety risks. These regular site visits help identify hazards at an early stage and review safety measures throughout the construction phase.
What is planned for 2027?
Construction of the photovoltaic plant is currently scheduled for completion in February 2027. Commissioning of the three new wind turbines is planned for spring 2027. The photovoltaic plant, with a planned capacity of 19.99 MWp, will complement the three new wind turbines, which have a combined capacity of 21.6 MW. Both will share a common grid connection point. A battery energy storage system is also being planned as a further addition to the hybrid park.
We will continue to provide updates here in the construction diary on the next stages of construction and the work taking place on site.

Steel tower sections, rotor blades and other components are ready on the assembly area. From here, they are lifted onto the towers using a crane.

One of the three new wind turbines has already been erected. It will be prepared for commissioning over the coming weeks.

A heavy-lift crane carefully guides a rotor blade towards the turbine hub.

The heavy-lift crane raises the rotor blade into position so that it can be attached to the hub.

The aerial view shows how the rotor blade is guided towards the hub using a specially designed lifting device.

The photo shows the hub of a new wind turbine. It is the central component of the rotor, to which the individual rotor blades are attached.

The nacelle bearing the VSB logo has already been installed on the tower. The rotor blades will be fitted next.
![[Translate to English:]](/fileadmin/_processed_/6/b/csm_06_SafetyWalk_IMG_2484__31e6ed744f.jpg)
During the joint safety tour, the participants inspect the construction site and the delivered turbine components.
![[Translate to English:]](/fileadmin/_processed_/a/6/csm_12_Reh_a5cd3c93c4.jpg)
Local wildlife can occasionally be spotted near the construction site. This roe deer was photographed at the edge of the construction area.
![[Translate to English:]](/fileadmin/_processed_/0/2/csm_09_Rueckbau-Fundamente-Altanlage_Bild__18__6b1869ff1a.jpg)
The foundations of the former wind turbines are being exposed in preparation for their removal.
![[Translate to English:]](/fileadmin/_processed_/a/2/csm_Bild__19__9b51c45400.jpg)
A bird’s-eye view of the removal of a former wind turbine foundation at Hybrid Park Löberitz. The foundation has already been broken up. The concrete rubble will now be crushed to a specified particle size for recycling.