  • Project information

    Commencement of construction 2026
    Commencement of production 2027
    Quantity of turbines 50-100
    Total Capacity 400-700 MW
  • Time schedule

    2019 Commencement of wind farm planning
    2021 Zoning agreement with municipality of Siikalatva
    2022-2023 Local master plan and environmental impact assessment (EIA)
    2024-2025 Building permits
    2026 Commencement of construction
    2027 Commercial commissioning of wind farm