Leuvanneva, Siikalatva and Siikajoki

Current information about Leuvanneva wind farm

Project area of Leuvanneva wind farm is located in Northern Ostrobothnia, in Siikalatva and Siikajoki municipalities. Wind farm is planned in approximately 12 000 hectares area between Kurunneva and Lahnasneva.

Project area consists of 50-100 wind turbines with total generation capacity of 400-700 MW. It is planned to use Fingrid’s Lumijärvi substation as a grid connection point.

Wind power local master plan and Environmental Impact Assessment (EIA) will be executed as a joint procedure.

 

News

No news found

Project information

Commencement of construction 2026
Commencement of production 2027
Quantity of turbines 50–100
Total Capacity 400–700 MW

Time schedule

2019 Commencement of wind farm planning
2021 Zoning agreement with municipality of Siikalatva
2022–2023 Local master plan and environmental impact assessment (EIA)
2024–2025 Building permits
2026 Commencement of construction
2027 Commercial commissioning of wind farm

Map

energy for you