Racibórz Wind Farm
Green energy – a safe future for our planet
VSB Group – Your Renewable Energy Partner
As a provider of comprehensive services in renewable energy projects, we focus on two main directions: respect for the natural environment and dialogue with residents. Together with the municipality of Pietrowice Wielkie, we have developed the Racibórz Wind Farm project, which includes 13 N117 / 3.2 MW turbines, hh 134 + 7 m.
At a glance
Environmentally friendly energy supply for approx. 36,000 households.
13 Nordex N117 / 3.2 MW turbines.
Supply to the network of the operator Tauron Dystrybucja S.A.
Location in the municipality of Pietrowice Wielkie, Racibórz district, Silesian voivodeship.
Comissioning in December 2024.
Potential to avoid emissions of about 44,000 tons of CO2 per year.
News from construction
Information about the wind park
Facts and timetable
We are a forward-thinking renewable energy project developer. Every single step of our wind farm planning is based on solid experience. This gives you and us the assurance of rapid construction progress.
Location | Silesian voivodeship, Racibórz district, municipality of Pietrowice Wielkie |
---|---|
Commissioning | December 2024 |
Energy supply | September 2024 |
Turbines | 13 Nordex N117 trubines |
Nominal power | 3.2 MW |
Hub height (height of the nacelle) | 134 m + 7 m concrete plinth |
Rotor blade length | 58,5 m |
Total turbine height | 185,5 m a.s.l. |
Startup speed | 3 m/s |
Shutdown speed | 25 m/s |
Connection to the grid | June 2024 |
Timeline | |
---|---|
October 2022 – May 2023 | Executive projects of construction, road and electrical industry |
June 2023 – December 2024 | Road works |
April 2023 – November 2023 | Foundations of turbines |
May 2023 – March 2024 | Medium voltage lines |
May 2023 – March 2024 | High voltage lines |
May 2023 – August 2024 | Substations |
January 2024 – April 2024 | Delivery of turbine components |
January 2024 – June 2024 | Installation of turbine components |
May 2024 – August 2024 | Turbine connections to the grid, consumers, commissioning, post-construction documentation, etc. |