Baranów-Rychtal Wind Farm

Wind is the energy of the future

Baranów-Rychtal Wind Farm – News

Green energy – a safe future for our planet

VSB Group – Your Renewable Energy Partner

As a provider of comprehensive services in the field of renewable energy projects, we focus on two main directions: respect for the natural environment and dialogue with residents. Together with the administrative districts of Gmina Baranów and Gmina Rychtal, we have created the Kępno Wind Farm project, which consists of two sub-projects: Baranów (four N131 turbines rated at 3.9 MW) and Rychtal (six N131 turbines rated at 3.9 MW + one N117 turbine rated at 3.6 MW). 

At a glance

Environmentally friendly energy supply for approx. 40,000 households.

Ten N131 wind turbines
+ one N117 turbine.

Power supply to the Energa operator’s grid.

Location in the administrative districts of Gmina Baranów and Gmina Rychtal, Kępno County, Greater Poland Voivodeship.

Putting into service in August 2023.

Ability to avoid CO2 emissions of nearly
45,000 tonnes per year.

News from construction

Want to know how far construction of the wind park has progressed? Join us during construction! We will keep you updated on the progress of the construction work.

Previous page

Information about the wind park

Facts and schedule

We are a forward-thinking renewable energy project developer. Every single step of our wind farm planning is based on solid experience. This gives you and us the assurance of rapid construction progress.

 

Location Baranów / Rychtal
Wind measurement 7m / s
Commissioning August 2023
Energy supply -
Turbines Nordex N131 oraz N117
Nominal power 3,9MW / 3,6MW
Hub height (nacelle height) Baranów 4x134m + Rychtal 7x120m (+4m)
Rotor blade length 64,4m
Total turbine height 199,5m
Switch-on speed 3m/s
Switch-off speed 25m/s
Connection to the supply grid December 2022
Timetable  
07.2021 – 04.2022 Detailed designs for construction, road and electrical works
12.2021 – 11.2021 Road works
01.2022 – 05.2022 Foundations of turbines
04.2022 – 10.2022 Medium voltage lines
04.2022 – 06.2022 High voltage lines
01.2022 – 05.2022 GPO substations
06.2022 – 10.2022 Supply and assembly of turbine components
12.2022 – 06.2023 Turbine connections to the grid, approvals, commissioning, as-built documentation, etc.