Baranów-Rychtal Wind Farm
Green energy – a safe future for our planet
VSB Group – Your Renewable Energy Partner
As a provider of comprehensive services in the field of renewable energy projects, we focus on two main directions: respect for the natural environment and dialogue with residents. Together with the administrative districts of Gmina Baranów and Gmina Rychtal, we have created the Kępno Wind Farm project, which consists of two sub-projects: Baranów (four N131 turbines rated at 3.9 MW) and Rychtal (six N131 turbines rated at 3.9 MW + one N117 turbine rated at 3.6 MW).
At a glance
Environmentally friendly energy supply for approx. 40,000 households.
Ten N131 wind turbines
+ one N117 turbine.
Power supply to the Energa operator’s grid.
Location in the administrative districts of Gmina Baranów and Gmina Rychtal, Kępno County, Greater Poland Voivodeship.
Putting into service in August 2023.
Ability to avoid CO2 emissions of nearly
45,000 tonnes per year.
News from construction
Want to know how far construction of the wind park has progressed? Join us during construction! We will keep you updated on the progress of the construction work.
Information about the wind park
Facts and schedule
We are a forward-thinking renewable energy project developer. Every single step of our wind farm planning is based on solid experience. This gives you and us the assurance of rapid construction progress.
Location | Baranów / Rychtal |
---|---|
Wind measurement | 7m / s |
Commissioning | August 2023 |
Energy supply | - |
Turbines | Nordex N131 oraz N117 |
Nominal power | 3,9MW / 3,6MW |
Hub height (nacelle height) | Baranów 4x134m + Rychtal 7x120m (+4m) |
Rotor blade length | 64,4m |
Total turbine height | 199,5m |
Switch-on speed | 3m/s |
Switch-off speed | 25m/s |
Connection to the supply grid | December 2022 |
Timetable | |
---|---|
07.2021 – 04.2022 | Detailed designs for construction, road and electrical works |
12.2021 – 11.2021 | Road works |
01.2022 – 05.2022 | Foundations of turbines |
04.2022 – 10.2022 | Medium voltage lines |
04.2022 – 06.2022 | High voltage lines |
01.2022 – 05.2022 | GPO substations |
06.2022 – 10.2022 | Supply and assembly of turbine components |
12.2022 – 06.2023 | Turbine connections to the grid, approvals, commissioning, as-built documentation, etc. |