Harmajapää, Suomussalmi and Puolanka

Current information about Harmajapää wind farm

Project area of Harmajapää wind farm is located in the municipalities of Puolanka and Suomussalmi. Wind farm is planned in approximately 7000 hectares area on the north side of the lake Suolijärvi.

Project area consists of 40–50 wind turbines with total generation capacity of 300–430 MW. 

Wind power local master plan and Environmental Impact Assessment (EIA) will be executed as a joint procedure.

No news found

Project information

Commencement of construction 2026
Commencement of production 2028
Quantity of turbines 40-50
Total Capacity 300-430 MW

Time schedule

2021 Commencement of wind farm planning
2021 Zoning agreement with Puolanka municipality
2022 Zoning initiative to Suomussalmi municipality
2023 Nature and environmental surveys
2023-2025 Local master plan and environmental impact assessment (EIA)
2025-2026 Building permits
2026 Commencement of construction
2028 Commercial commissioning of wind farm

Map

VSB Gruppe - Outojänkä, Tervola - Finnland